Activities last week:
Fixed bustage, release activities for TB 57, looked for regressions, various reviews, misc. bug fixes, sheriffing.
Notable: Finally fixed MS Outlook import, broken since TB 38 (June 2015).
Obstacles and impediments: Slow reviews as noted below (one, two and three month delay), aka, the Mailnews Crisis. Little support by peers.
Lack of response from M-C in some M-C bustages (NSPR).
Contract not renewed, see below.
General remarks: C-C tree status: Deteriorating, no manpower to investigate various intermittent test failures.
This is my last report to this mailing list since my contract wasn't renewed. So good luck to all my peers with maintaining and releasing Thunderbird.
Jörg.
=== Dates (3) ===
Fr 10 Nov 2017: 2.62 hours - last day.
Th 9 Nov 2017: 4.80 hours
We 8 Nov 2017: 7.62 hours
=== Activities ===
Administration 45 min, 0.75 hours ( 5.0%)
Bustage fixes 443 min, 7.38 hours (49.1%)
BMO follow-up 109 min, 1.82 hours (12.1%)
Volunteer Triaging 10 min, 0.17 hours ( 1.1%)
Regression Triaging 125 min, 2.08 hours (13.9%)
Sheriffing 87 min, 1.45 hours ( 9.6%)
Releases (incl. Notes) 58 min, 0.97 hours ( 6.4%)
Uplifts 15 min, 0.25 hours ( 1.7%)
Reviews 10 min, 0.17 hours ( 1.1%)
=== Totals ===
902 min, 15.03 hours, 5.01 hours per day
Thanks for the report and your hard work on the project! We're looking
forward to getting the paperwork out of the way and your contract renewed.
In the meanwhile, I'd appreciate if others could lend a helping hand and
take a look at bustages. At the very least, it would be great to have
bugs filed for issues that are directly visible on treeherder. For the
meanwhile maybe we can go back to starring bustages.
Philipp
On 11/16/17 10:42 PM, Jörg Knobloch wrote:
Activities last week:
Fixed bustage, release activities for TB 57, looked for regressions,
various reviews https://hg.mozilla.org/comm-central/pushloghtml,
misc. bug fixes, sheriffing.
Notable: Finally fixed MS Outlook import, broken since TB 38 (June 2015).
*Obstacles and impediments:
*Slow reviews as noted below (one, two and three month delay), aka,
the Mailnews Crisis. Little support by peers.
Lack of response from M-C in some M-C bustages (NSPR).
Contract not renewed, see below.
*General remarks:
*C-C tree status: Deteriorating, no manpower to investigate various
intermittent test failures.
This is my last report to this mailing list since my contract wasn't
renewed. So good luck to all my peers with maintaining and releasing
Thunderbird.
Jörg.
=== Dates (3) ===
Fr 10 Nov 2017: 2.62 hours- last day.
Th 9 Nov 2017: 4.80 hours
We 8 Nov 2017: 7.62 hours
=== Activities ===
Administration 45 min, 0.75 hours ( 5.0%)
Bustage fixes 443 min, 7.38 hours (49.1%)
BMO follow-up 109 min, 1.82 hours (12.1%)
Volunteer Triaging 10 min, 0.17 hours ( 1.1%)
Regression Triaging 125 min, 2.08 hours (13.9%)
Sheriffing 87 min, 1.45 hours ( 9.6%)
Releases (incl. Notes) 58 min, 0.97 hours ( 6.4%)
Uplifts 15 min, 0.25 hours ( 1.7%)
Reviews 10 min, 0.17 hours ( 1.1%)
=== Totals ===
902 min, 15.03 hours, 5.01 hours per day
Maildev mailing list